HS2's Euston tunnel passed its halfway point this week, according to a 23 November 2026 release from HS2 Ltd and a report by New Civil Engineer the same day. The two tunnel boring machines, named Karen and Madeleine, had by 17 November bored a combined 2.25 miles of the 4.5-mile twin-bore tunnel.
The drive so far
The machines left the future Old Oak Common super hub in January and March 2026 and now sit in the area between West Hampstead and Kilburn High Road. Each weighs 1,624 tonnes, advances at about 16 metres a day and works around the clock. The tunnel is HS2's fifth and final deep-bored tunnel, and the Skanska Costain STRABAG joint venture, HS2's London tunnels contractor, operates the machines. NCE puts the completion of the tunnel in 2027.
The programme expects to excavate 1.5 million tonnes of material and to line the tunnel with 48,294 concrete segments made in Hartlepool in North East England. The machines will stop underground on the approach to Euston, their cutterheads will be removed in the Euston cavern, and parts of their outer shields will stay behind the finished lining.
Programme context
HS2 chief executive Mark Wild described the programme as being in the last phases of a "root and branch" reset intended to deliver the railway safely at the lowest reasonable cost, so the wider timetable and cost remain open. At Euston itself, main excavation for the new platforms has begun, and HS2 expects to move up to 170,000 tonnes of spoil by rail for reuse in Bedfordshire, of which 35,000 tonnes were moved in trials. At Old Oak Common, a tunnel breakthrough into the station box in early November created a continuous route towards West Ruislip.
Why it matters for delivery teams
The Euston drive passes under dense London ground up to 50 metres down, so settlement monitoring, segment logistics and rail-borne spoil removal all depend on tightly shared data. The editors see it as a live example of how long linear programmes use digital models to coordinate precast supply, machine progress and community-facing logistics while the commercial plan is still being reset.
Image: Euston station, London, where HS2's Euston tunnel ends. Photo: mattbuck, CC BY-SA 3.0, via Wikimedia Commons.
Sources checked for this story
- HS2 tunnel boring machines reach halfway on journey to Euston — HS2 Ltd, November 23, 2026
- HS2 tunnels to Euston pass halfway point — New Civil Engineer, November 23, 2026