The Ministry of Agriculture and Food Security of the Democratic Republic of the Congo, through the national coordination unit of the Programme National de Développement Agricole (PNDA), has opened international bidding for the rehabilitation into a paved road of the RP111 road, from the RN1 junction (PK 00+000) through Malanga, Kiasungwa and Kimbemba to the Luozi ferry (PK 94+628). The notice was dated 9 October 2026 and bids close on 24 November 2026 at 14:00 Kinshasa time (UTC+1).
The brief
The 94.628 km two-lane road will combine a rigid reinforced concrete pavement on sections with steep gradients above 5% and a flexible asphalt concrete pavement elsewhere. The works are split into three lots, each with a 10-month execution period, and bidders may bid for one or more lots:
- Lot 1: RN1 junction to Kumbi village (PK 00+000 to 29+640), 29.64 km, including about 261,425 m3 of earthworks, 6,928 m3 of concrete wearing course on slopes and 9,161 m of drains.
- Lot 2: Kumbi to Kiyadi (PK 29+640 to 67+000), 37.36 km, including about 329,515 m3 of earthworks and 8,262 m3 of asphalt concrete.
- Lot 3: Kiyadi to Kimbemba (PK 67+000 to 94+628), 27.628 km, including the access ramps to the ferry (2,400.6 m3 of concrete).
Key terms from the notice: reference ZR-MINAGRI-563391-CW-RFB; financing from World Bank grant D8690-ZR and credit 69510-ZR under project P169021; international competitive procurement under the World Bank Procurement Regulations (September 2025 edition), open to bidders from eligible countries. Rated criteria (technical and non-price) weigh 60% and bid cost 40%. Each lot needs a bank guarantee of US$200,000, plus a declaration on sexual exploitation, abuse and harassment and a local labour commitment. The bidding document, in French, costs US$250, non-refundable. Estimated contract value: not stated in the notice.
A short history
The PNDA was approved by the World Bank on 25 June 2021 with a total commitment of US$520 million and is implemented by the Ministry of Agriculture. Its stated objective is to improve agricultural productivity and market access for smallholder farmers in selected areas, which is why a farm-to-market road such as the RP111 sits inside an agriculture programme. The road ends at the ferry crossing at Luozi, on the Congo River.
Guidance for bidders
These are suggestions from the ConstruBIM editors, not the employer's words and not legal or procurement advice.
- Choose lots with care. Each lot runs 10 months; bidding for several lots means proving plant, crews and concrete supply for parallel work.
- Quality counts for 60%. Explain how you will build the concrete slope sections, drainage and the ferry ramps, not only the asphalt.
- Model the earthworks. A terrain model with cut and fill balance per lot supports your method statement and shows haulage logic to evaluators.
- Prepare the guarantees and declarations early. Three US$200,000 guarantees, the sexual exploitation and abuse declaration and the local labour commitment are all required with the bid.
- Allow for courier time. Electronic bids are not accepted; documents can be sent by DHL at the bidder's cost and risk.
How to bid
Request the bidding document in writing from the PNDA national coordination unit, 110 Boulevard du 30 juin, 5th floor, Kinshasa-Gombe (pndardc@gmail.com), and pay US$250 by transfer to the account named in the notice. Deliver bids to the same address by 24 November 2026 at 14:00 local time (UTC+1); technical envelopes are opened in public at 14:30 the same day, and late bids are rejected. Official notice: World Bank notice OP00473977.
Image: the Kongo Central provincial government building in Matadi. Photo: Shaloom Yave, CC BY-SA 4.0, via Wikimedia Commons.
Sources checked for this story
- Travaux de réhabilitation en route revêtue de l'Axe Routier RP111 (OP00473977) — World Bank, October 8, 2026
- National Agriculture Development Program (P169021) — World Bank, October 14, 2026